Project
Project Name Ekta Brooklyn Park Phase 3 |
Locality Virar West |
Sub Locality -- |
Builder's Name Ekta World |
RERA Number(s) P99000000148 |
Price Range 0.37 cr to 0.39 cr |
Configuration Range 1 BHK , 2 BHK |
Construction Status Ready to Move |
Project Layout | Project Layout by RERA | ||
Number of Towers | 3 | Total Building Count | 3 |
Number of Units | 165 | Sanctioned Building Court | 3 |
Type of Development | Complex | Proposed but not sanctioned buildings count | -- |
Land Parcel | 919.22 Sqmt | Aggregate Area (in sqmts) of recreational open space | 785 |
Layout | View Layout |
Project Name Brooklyn Park Phase 3 |
Project Type Residential |
Project Status On Going Project |
Proposed Date of Completion 2020-11-25 |
Revised Proposed Date of Completion 2020-02-28 |
Number of Flats Sold 161 |
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned) 0 |
Total FSI 7981.91 |
Total Built-up Area as per approved FSI 0 |
Sports |
Security & Sanitation |
Business & Hospitality |
Leisure |
Green Features |
Fire Safety |
Vertical Transportation |
Amenities | Available | Percentage | Detail |
---|---|---|---|
Internal Roads And Footpath | No | -- | Na |
Water Conservation Rainwater Harvest | Yes | 90 | Work In Progress |
Energy Management | Yes | 90 | Work Completed |
Fire Protection And Fire Safety | Yes | 100 | Work Completed |
Electrical Meter Room | Yes | 70 | Work In Progress |
Children Play Area | Yes | 100 | Gazebo Fixed. |
Aggregate Area Of Recreation | Yes | 20 | Yet To Start |
Open Parking | No | -- | Na |
Water Supply | Yes | 90 | Inside Work Completed |
Sewage | Yes | 80 | Work In Progress |
Storm Water Drains | Yes | 90 | Work In Progress |
Landscaping And Tree Plantation | Yes | 100 | Completed |
Street Lightening | No | -- | Na |
Community Buildings | No | -- | Na |
Treatment And Disposal | Yes | 80 | Work In Progress |
Solid Waste Management | Yes | 100 | Oragnic Waste Composter Iinstalled. |
Parking Name | Proposed | Booked | Work Done |
---|---|---|---|
Garages | -- | -- | -- |
Covered Parking | 201 | 9 | -- |
Parking Available
Basement or over-ground with ramp parking
Car Parking Units
201
Power Backup
For Common Areas