Project
Project Name West Bay |
Locality Bandra (west) |
Sub Locality Santosh Nagar |
Builder's Name Transcon |
RERA Number(s) P51800001494 |
Price Range -- |
Configuration Range 3 BHK , Duplex |
Construction Status Nearing Ready |
Project Layout | Project Layout by RERA | ||
Number of Towers | 1 | Total Building Count | 1 |
Number of Units | 62 | Sanctioned Building Court | 1 |
Type of Development | Stand Alone | Proposed but not sanctioned buildings count | -- |
Land Parcel | 0.36 Acre | Aggregate Area (in sqmts) of recreational open space | -- |
Layout | View Layout |
Project Name West Bay |
Project Type Residential |
Project Status On-going Project |
Proposed Date of Completion 2017-12-31 |
Revised Proposed Date of Completion 2022-06-30 |
Number of Flats Sold 33 |
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned) 3885.58 |
Total FSI 7408.93 |
Total Built-up Area as per approved FSI 3523.35 |
Sports |
Green Features |
Security & Sanitation |
Amenities | Available | Percentage | Detail |
---|---|---|---|
Water Conservation, Rain Water Harvesting : | Yes | -- | - |
Energy Management : | Yes | -- | Only Rain Water Harvesting |
Fire Protection And Fire Safety Requirements : | Yes | 30 | Ff Works For 9 Flats Done With Pumps Installation |
Electrical Meter Room, Sub-station, Receiving Station : | Yes | 25 | Electrical Meters For 18 No Flats Done |
Aggregate Area Of Recreational Open Space : | Yes | -- | Common Rg 786.5 Sq Mtrs For Entire Property |
Open Parking : | No | -- | Na |
Water Supply : | Yes | 27 | Water Supply To 18 Flats Given |
Sewerage (chamber, Lines, Septic Tank , Stp) : | Yes | 50 | Drainage Connections Done |
Storm Water Drains : | Yes | 25 | Front Side Done |
Landscaping & Tree Planting : | Yes | -- | - |
Street Lighting : | No | -- | Na |
Community Buildings : | No | -- | Na |
Treatment And Disposal Of Sewage And Sullage Water : | Yes | 5 | Work In Progress |
Solid Waste Management And Disposal : | Yes | -- | Stp Tank Rcc Work Done |
Internal Roads & Footpaths : | No | -- | Na |
Parking Name | Proposed | Booked | Work Done |
---|---|---|---|
Garages | -- | -- | -- |
Covered Parking | 87 | 35 | 86 |
Parking Available
Car Parking Units
Power Backup
Complete Power Backup