1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gated Community

Tower Name A Lotus Fire Exits 2
Total Floors 10 Refuge Areas 1
Number of Elevators 2 Configurations Present Studio,1 BHK
Flats Per Floor 11 Tower Layout
Wing Name A Lotus Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 10
Number of Plinth 1 Number of Stilts 1
Wing Name B Lotus Number of Podium --
Number of Basements -- Number of Slabs of Superstructure --
Number of Plinth -- Number of Stilts --
Possession Availability
Possession Date
Possession Availability as per RERA
Proposed Date of Completion 31-03-2019
Revised Proposed Date of Completion 31-03-2019
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor 75
1 X Number Of Slabs Of Super Structure 35
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --
View More