Project
Project Name Sethia Grandeur |
Locality Bandra (east) |
Sub Locality Teacher's Colony |
Builder's Name Sethia Infrastructure |
RERA Number(s) P51800009020 |
Price Range 0.95 cr to 3.88 cr |
Configuration Range 2 BHK , 3.5 BHK |
Construction Status Sold Out |
Project Layout | Project Layout by RERA | ||
Number of Towers | 1 | Total Building Count | 1 |
Number of Units | 95 | Sanctioned Building Court | 1 |
Type of Development | Stand Alone | Proposed but not sanctioned buildings count | -- |
Land Parcel | 0.22 Acre | Aggregate Area (in sqmts) of recreational open space | 46.06 |
Layout | View Layout |

Project Name Sethia Grandeur |
Project Type Residential |
Project Status On-going Project |
Proposed Date of Completion 2019-12-31 |
Revised Proposed Date of Completion 2020-12-30 |
Number of Flats Sold 95 |
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned) 1139.45 |
Total FSI 6928.78 |
Total Built-up Area as per approved FSI 5789.33 |
Sports |
Leisure |
Business & Hospitality |
Green Features |
Security & Sanitation |
Amenities | Available | Percentage | Detail |
---|---|---|---|
Internal Roads & Footpaths : | Yes | 100 | Completed |
Water Conservation, Rain Water Harvesting : | Yes | 100 | Completed |
Energy Management : | No | -- | Na |
Fire Protection And Fire Safety Requirements : | Yes | 90 | Work In Progress |
Electrical Meter Room, Sub-station, Receiving Station : | Yes | 90 | Work In Progress |
Swimming Pool And Fitness Center : | Yes | 100 | Completed |
Aggregate Area Of Recreational Open Space : | No | -- | Na |
Open Parking : | Yes | 100 | Completed |
Water Supply : | Yes | 100 | Completed |
Sewerage (chamber, Lines, Septic Tank , Stp) : | Yes | 100 | Completed |
Storm Water Drains : | Yes | 100 | Completed |
Landscaping & Tree Planting : | Yes | 100 | Completed |
Street Lighting : | No | -- | Na |
Community Buildings : | No | -- | Na |
Treatment And Disposal Of Sewage And Sullage Water : | Yes | 100 | Completed |
Solid Waste Management And Disposal : | Yes | 100 | Completed |
Parking Name | Proposed | Booked | Work Done |
---|---|---|---|
Garages | -- | -- | -- |
Covered Parking | 82 | 45 | 27 |
Parking Available
Basement or over-ground with ramp parking

Car Parking Units
82

Power Backup
Not Mentioned
