Dedicated locality research platform

1st Habitable Floor

1st floor

Views
Road View / No View
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Gated Society

Tower Name Mukund Apartment 1-A Wing Fire Exits --
Total Floors 4 Refuge Areas --
Number of Elevators 1 Configurations Present 1 BHK,2 BHK
Flats Per Floor 4 Tower Layout
Tower Name Mukund Apartment 1-B Wing Fire Exits --
Total Floors 3 Refuge Areas --
Number of Elevators 1 Configurations Present 1 BHK,2 BHK
Flats Per Floor 4 Tower Layout
Tower Name Mukund Apartment 2-A Wing Fire Exits --
Total Floors 15 Refuge Areas --
Number of Elevators 2 Configurations Present 1 BHK,2 BHK
Flats Per Floor 4 Tower Layout
Tower Name Mukund Apartment 2-B Wing Fire Exits --
Total Floors 5 Refuge Areas --
Number of Elevators 1 Configurations Present 1 BHK,2 BHK
Flats Per Floor 4 Tower Layout
Wing Name Mukund Apartment 1 - A wing Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 4
Number of Plinth 1 Number of Stilts --
Wing Name Mukund Apartment 1 - B wing Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 3
Number of Plinth 1 Number of Stilts --
Wing Name Mukund Apartment 2 - A Wing Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 15
Number of Plinth 1 Number of Stilts --
Wing Name Mukund Apartment 2 - B Wing Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 5
Number of Plinth 1 Number of Stilts --
Wing Name CFC Building Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 3
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 31-12-2022
Possession Availability as per RERA
Proposed Date of Completion 30-12-2023
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation --
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --
View More
View Less
Amenities