1st Habitable Floor

7 th

Views
--
Floor to Ceiling Height

--

Project Theme

--

Tower Name Raheja Artesia Fire Exits 2
Total Floors 58 Refuge Areas 5
Number of Elevators 9 Configurations Present 2 BHK,4 BHK,Duplex
Flats Per Floor 4 Tower Layout
Wing Name ARTESIA - RESIDENTIAL WING CONSTRUCTED ON PROJECT LAND Number of Podium 5
Number of Basements 2 Number of Slabs of Superstructure 58
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 30-06-2023
Possession Availability as per RERA
Proposed Date of Completion 30-06-2019
Revised Proposed Date of Completion 30-06-2023
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 92
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 65
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 38
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 83
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 80
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 61