Dedicated locality research platform

1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gated Community

Tower Name Northern Hills Fire Exits 3
Total Floors 65 Refuge Areas 5
Number of Elevators 5 Configurations Present 2 BHK,3 BHK
Flats Per Floor 8 Tower Layout View Layout
Wing Name Northern Supremus - Commercial Number of Podium --
Number of Basements 3 Number of Slabs of Superstructure 11
Number of Plinth 1 Number of Stilts 1
Wing Name Residential Wing A & B Number of Podium 10
Number of Basements 3 Number of Slabs of Superstructure 65
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 31-12-2022
Possession Availability as per RERA
Proposed Date of Completion 30-06-2026
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation 80
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --
View More
View Less
Amenities
Sports
  • Kids Play Area
© Propscience.com. All Rights Reserved.