Dedicated locality research platform

1st Habitable Floor

--

Views
--
Floor to Ceiling Height

--

Project Theme

--

Tower Name Palacio Fire Exits --
Total Floors 40 Refuge Areas --
Number of Elevators 5 Configurations Present 2 BHK,3 BHK
Flats Per Floor 2 Tower Layout View Layout
Wing Name Ruparel Palacio Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 24
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 31/12/2022
Possession Availability as per RERA
Proposed Date of Completion 30-06-2023
Revised Proposed Date of Completion 01-01-1970
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.