1st Habitable Floor

Ground Floor

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

--

Tower Name Tower 1 Fire Exits 2
Total Floors 53 Refuge Areas --
Number of Elevators 3 Configurations Present 1.5 BHK
Flats Per Floor 4 Tower Layout View Layout
Tower Name Tower 3 Fire Exits 4
Total Floors 36 Refuge Areas --
Number of Elevators 6 Configurations Present 1.5 BHK
Flats Per Floor 8 Tower Layout View Layout
Tower Name Tower 4 Fire Exits 2
Total Floors 36 Refuge Areas --
Number of Elevators 4 Configurations Present 2 BHK
Flats Per Floor 6 Tower Layout View Layout
Tower Name Tower 2 Fire Exits 1
Total Floors 53 Refuge Areas 1
Number of Elevators 3 Configurations Present 1.5 BHK
Flats Per Floor 4 Tower Layout View Layout
Wing Name Tower 1 and 2 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 44
Number of Plinth 1 Number of Stilts 1
Wing Name Tower 3 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 44
Number of Plinth 1 Number of Stilts 1
Wing Name Tower 4 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 42
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 30-04-2021
Possession Availability as per RERA
Proposed Date of Completion 29-02-2020
Revised Proposed Date of Completion 30-04-2022
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 100
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 100
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 100
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 100
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 90
View More
View Less