1st Habitable Floor

--

Views
--
Floor to Ceiling Height

--

Project Theme

--

Wing Name K Mordani Celyn Number of Podium 2
Number of Basements 1 Number of Slabs of Superstructure 20
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date
Possession Availability as per RERA
Proposed Date of Completion 31-10-2019
Revised Proposed Date of Completion 30-04-2021
Sr. No Task/Activity % Work Done
1 Excavation 90
1 X Number Of Basement(s) And Plinth 60
1 X Number Of Podiums 50
1 Stilt Floor 50
1 X Number Of Slabs Of Super Structure 30
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 20
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 20
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --
View More
View Less