Dedicated locality research platform

1st Habitable Floor

1st Floor

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Greater than 10 feet

Project Theme

NA

Tower Name Runwal Bliss Wing - B Fire Exits --
Total Floors 53 Refuge Areas --
Number of Elevators 6 Configurations Present 2 BHK
Flats Per Floor 6 Tower Layout View Layout
Wing Name Wing B Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 53
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 31-12-2022
Possession Availability as per RERA
Proposed Date of Completion 31-12-2021
Revised Proposed Date of Completion 30-12-2023
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 92
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 19
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 58
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 100
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 18
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.