Dedicated locality research platform

1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gated Community

Tower Name Shree Sagar Apartment Fire Exits 1
Total Floors 11 Refuge Areas 1
Number of Elevators 1 Configurations Present Studio,1 BHK
Flats Per Floor 12 Tower Layout
Wing Name Sagar Apartment Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 11
Number of Plinth 1 Number of Stilts 8
Possession Availability
Possession Date 01-09-2023
Possession Availability as per RERA
Proposed Date of Completion 01-03-2024
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation 10
1 X Number Of Basement(s) And Plinth 10
1 X Number Of Podiums 10
1 Stilt Floor 10
1 X Number Of Slabs Of Super Structure 10
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 10
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 10
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 10
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 10
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 10
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.