Dedicated locality research platform

1st Habitable Floor

1st

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

2 hectares of greens, 50+ lifestyle and convenience amenitie ...

Tower Name Tower 7 - 12 Fire Exits 2
Total Floors 33 Refuge Areas 6
Number of Elevators 6 Configurations Present 1 BHK,2 BHK
Flats Per Floor 12 Tower Layout View Layout
Wing Name TOWER 7 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Wing Name TOWER 8 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Wing Name TOWER 9 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Wing Name TOWER 10 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Wing Name TOWER 11 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Wing Name TOWER 12 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 30-06-2028
Possession Availability as per RERA
Proposed Date of Completion 30-06-2028
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation --
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.