Dedicated locality research platform

1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gated Community

Tower Name Natasha Enclave Fire Exits 2
Total Floors 21 Refuge Areas 2
Number of Elevators 4 Configurations Present 1 BHK,2 BHK
Flats Per Floor 9 Tower Layout View Layout
Wing Name Natasha Enclave Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 21
Number of Plinth 1 Number of Stilts 6
Possession Availability
Possession Date 31/12/2023
Possession Availability as per RERA
Proposed Date of Completion 31-12-2021
Revised Proposed Date of Completion 30-06-2024
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 90
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 80
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 95
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 98
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr 80
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.