Tower Name Building 1 -Bolton Fire Exits 2
Total Floors 21 Refuge Areas 2
Number of Elevators 2 Configurations Present 1 BHK,2 BHK
Flats Per Floor 5 Tower Layout View Layout
Tower Name Building 2 - Stark Fire Exits 2
Total Floors 14 Refuge Areas 1
Number of Elevators 2 Configurations Present 1 BHK,2 BHK
Flats Per Floor 5 Tower Layout View Layout
Wing Name Bldg No 1 Bolton Number of Podium 1
Number of Basements -- Number of Slabs of Superstructure 29
Number of Plinth 1 Number of Stilts 1
Wing Name Bldg No 2 Stark Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 14
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date
Possession Availability as per RERA
Proposed Date of Completion 31-12-2020
Revised Proposed Date of Completion 30-06-2022
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 23
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 90
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 15
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --