1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gym and D'mart in walk able distance.

Tower Name AABIEL HEIGHTS Fire Exits --
Total Floors 20 Refuge Areas 3
Number of Elevators 2 Configurations Present 1 BHK
Flats Per Floor 5 Tower Layout View Layout
Tower Name AABIEL HEIGHTS Fire Exits --
Total Floors 20 Refuge Areas 3
Number of Elevators 2 Configurations Present 2 BHK
Flats Per Floor 2 Tower Layout View Layout
Wing Name AABIEL HEIGHTS Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 21
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 31-07-2021
Possession Availability as per RERA
Proposed Date of Completion 31-08-2021
Revised Proposed Date of Completion 28-02-2022
Sr. No Task/Activity % Work Done
1 Excavation 50
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor 80
1 X Number Of Slabs Of Super Structure 60
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --