Dedicated locality research platform

1st Habitable Floor

1st

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Gated Community

Tower Name HighLand Park-Building 2 -K25 Wing A Phase 2 Fire Exits 2
Total Floors 33 Refuge Areas 3
Number of Elevators 2 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 6 Tower Layout View Layout
Wing Name BUILDING 2- K25- WING A Number of Podium 2
Number of Basements -- Number of Slabs of Superstructure 33
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 09/04/2019
Possession Availability as per RERA
Proposed Date of Completion 31-12-2023
Revised Proposed Date of Completion 30-12-2024
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 85
1 Stilt Floor 85
1 X Number Of Slabs Of Super Structure 38
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 14
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 2
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 38
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 8
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --