Tower Name A1 Fire Exits 2
Total Floors 32 Refuge Areas 3
Number of Elevators 3 Configurations Present 1 BHK
Flats Per Floor 8 Tower Layout View Layout
Tower Name A2 Fire Exits 2
Total Floors 31 Refuge Areas --
Number of Elevators 2 Configurations Present 1 BHK
Flats Per Floor 6 Tower Layout View Layout
Wing Name A1 Number of Podium 2
Number of Basements 2 Number of Slabs of Superstructure 32
Number of Plinth 1 Number of Stilts 1
Wing Name A2 Number of Podium 2
Number of Basements 1 Number of Slabs of Superstructure 31
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 31/12/2024
Possession Availability as per RERA
Proposed Date of Completion 31-12-2023
Revised Proposed Date of Completion 30-12-2024
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 65
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 81
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 40
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 50
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 30
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --