Commercials

Land Details & Documentation
Land Title Free Hold
Documentation
Title report View
Project blueprint Layout View
Building plan approval View
Status of formation of legal entities View
Litigation Details
Project Name Court Name Case Number Case Type Preventive / Injunction / Interim order passed? Petition Name Other Petition Details Year Present Status Documents
Palava Lakeside A To H Civil Judge Jd Kalyan 345 Civil No Suit NA 2014 Matter Setteld And Withdrawn Na
Customer Complaints
Complaint Number Complaint Name Order Type Remarks The Order is Comments PDF of Complaint
Cc006000000000913 Mikita Final Order Final Order Ruling By Maharera The Complainant Has Unconditionally Withdrawn Her Complaint Vide Application Dated 7h April 2018, Citing Personal Reasons. View
Cc006000000023002 Avaneesh Pramod Gupta Final Order Final Order Ruling By Maharera Ln View O{ The Above Facts, The Respondent Is Not Liable To Pay Interest On Delay To The Complainants, As Per Section 18 Of The Real Estate (regulation And Development) Act, 2016. The Complainants Are Advised To Take Possession Of Their Apartments, As The Said Apartment Is Now ,ready For Occupation. Alternatively If The Complainants Intend To Withdraw From The Said Project Then Such Withdrawal Shall Be Guided By The Terms And Conditions Of The Said Agreements. Consequently, The Matter Are View
Cc006000000056404 Suryakant Y. Jadhav Final Order Final Order Ruling By Maharera The Respondent Is Not Liable To Pay Interest On Delay To The Complainants, As Per Section 18 Of The Real Estate (regulation And Development) Act, 2016. The Complainants Are Advised To Take Possession Of Their Apartments, As D1e Said Apartment Is Now ,ready For Occupation. Alternatively If The Complainants Intend To Withdraw From The Said Project Then Such Withdrawal Shall Be Guided By The Terms And Conditions Of The Said Agreements. Consequently, The Matter Are Hereby Disposed Of View
Cc006000000056404 Suryakant Jadhav Huf Final Order Final Order Ruling By Maharera The Respondent Is Not Liable To Pay Interest On Delay To The Complainants, As Per Section 18 Of The Real Estate (regulation And Development) Act, 2016. The Complainants Are Advised To Take Possession Of Their Apartments, As D1e Said Apartment Is Now ,ready For Occupation. Alternatively If The Complainants Intend To Withdraw From The Said Project Then Such Withdrawal Shall Be Guided By The Terms And Conditions Of The Said Agreements. Consequently, The Matter Are Hereby Disposed Of View
Cc006000000056405 Suryakant Y. Jadhav Final Order Final Order Ruling By Maharera Ln View O{ The Above Facts, The Respondent Is Not Liable To Pay Interest On Delay To The Complainants, As Per Section 18 Of The Real Estate (regulation And Development) Act, 2016. The Complainants Are Advised To Take Possession Of Their Apartments, As D1e Said Apartment Is Now ,ready For Occupation. 5. Alternatively If The Complainants Intend To Withdraw From The Said Project Then Such Withdrawal Shall Be Guided By The Terms And Conditions Of The Said Agreements. 6. Consequently, The Matte View
Cc006000000056405 Suryakant Y. Jadhav Huf Final Order Final Order Ruling By Maharera Ln View O{ The Above Facts, The Respondent Is Not Liable To Pay Interest On Delay To The Complainants, As Per Section 18 Of The Real Estate (regulation And Development) Act, 2016. The Complainants Are Advised To Take Possession Of Their Apartments, As D1e Said Apartment Is Now ,ready For Occupation. 5. Alternatively If The Complainants Intend To Withdraw From The Said Project Then Such Withdrawal Shall Be Guided By The Terms And Conditions Of The Said Agreements. 6. Consequently, The Matte View
Cc006000000054828 Kishore Prakash Kulkarni Final Order Final Order Ruling By Maharera The Complainant Is Advised To Take Possession Of His Apartment By Making The Requisite Payments. 5. Consequently, The Matter Is Hereby Disposed Of. View
Construction Approvals
Commencement Certificate View
Occupation certificate NA
FSI Details
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned)2538.00
Total FSI 56034.95
Total Built-up Area as per approved FSI53496.95