Builder Information
Project Name
Shantistar Shanti One
Locality
Mira Road East
Sub Locality
Shanti Park
Builder's Name
Shantistar Builders
RERA Number(s)
P51700003278
Price Range
0.56 cr to 0.87 cr
Configuration Range
1 BHK , 2 BHK , 3 BHK
Construction Status
Under Construction


Master Layout
Project Layout Project Layout by RERA
Number of Towers 1 Total Building Count 1
Number of Units 78 Sanctioned Building Court 1
Type of Development Stand Alone Proposed but not sanctioned buildings count --
Land Parcel 1,512.00 Sqmt Aggregate Area (in sqmts) of recreational open space --
Layout View Layout
Project Overview
Project Name
Shanti One
Project Type
Residential
Project Status
On-going Project
Proposed Date of Completion
2019-12-31
Revised Proposed Date of Completion
2022-06-30
Number of Flats Sold
13
Built-up Area as per proposed FSI
(in sqmts)(Proposed but not sanctioned)

3160
Total FSI
5266.45
Total Built-up Area as per approved FSI
2106.45

Amenities
Security & Sanitation
  • Society Office
  • Security System / CCTV
  • Intercom Facility
Green Features
  • Waste Segregation
  • Rain Water Harvesting
  • Water Storage
Leisure
  • Pet Friendly
Construction Status of Amenities - as per RERA
Amenities Available Percentage Detail
Internal Roads & Footpaths : No -- Na
Water Conservation, Rain Water Harvesting : Yes -- Not Yet Started
Energy Management : Yes -- Not Yet Started
Fire Protection And Fire Safety Requirements : Yes -- Not Yet Started
Electrical Meter Room, Sub-station, Receiving Station : Yes -- Not Yet Started
Aggregate Area Of Recreational Open Space : Yes -- Not Yet Started
Open Parking : No -- Na
Water Supply : Yes -- Will Be Provided By Mbmcsewerage (chamber, Lines, Septic Tank , Stp) :
Sewerage (chamber, Lines, Septic Tank , Stp) : Yes 20 Work In Progress
Storm Water Drains : Yes 20 No Stp Or Septic Tank
Landscaping & Tree Planting : Yes -- Work In Progress
Street Lighting : No -- Na
Community Buildings : No -- Na
Treatment And Disposal Of Sewage And Sullage Water : No -- Na
Solid Waste Management And Disposal : No -- Na
Construction Status - as per RERA
Parking Name Proposed Booked Work Done
Garages -- -- --
Covered Parking 27 -- --

Parking Available

Car Parking Units

Power Backup

-