1st Habitable Floor

3rd

Views
--
Floor to Ceiling Height

--

Project Theme

Strategically constructed

Tower Name Wing A Fire Exits 2
Total Floors 15 Refuge Areas --
Number of Elevators 3 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 8 Tower Layout View Layout
Tower Name Wing B Fire Exits 2
Total Floors 15 Refuge Areas --
Number of Elevators 3 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 8 Tower Layout View Layout
Wing Name Building 1- A Wing Number of Podium 2
Number of Basements -- Number of Slabs of Superstructure 14
Number of Plinth 1 Number of Stilts 1
Wing Name Building 1- B Wing Number of Podium 2
Number of Basements -- Number of Slabs of Superstructure 14
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 01/05/2020
Possession Availability as per RERA
Proposed Date of Completion 01-12-2019
Revised Proposed Date of Completion 01-11-2020
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 40
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 50
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 60
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 80
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr 5