Dedicated locality research platform

1st Habitable Floor

2nd

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Strategically constructed

Tower Name PRAJAPATI MAGNUM WING A Fire Exits 2
Total Floors 19 Refuge Areas --
Number of Elevators 2 Configurations Present 2 BHK,3 BHK
Flats Per Floor 4 Tower Layout View Layout
Tower Name PRAJAPATI MAGNUM WING B Fire Exits 2
Total Floors 19 Refuge Areas --
Number of Elevators 2 Configurations Present 2 BHK,3 BHK
Flats Per Floor 4 Tower Layout View Layout
Tower Name PRAJAPATI MAGNUM WING C Fire Exits 2
Total Floors 19 Refuge Areas --
Number of Elevators 2 Configurations Present 2 BHK,3 BHK
Flats Per Floor 4 Tower Layout View Layout
Wing Name PRAJAPATI MAGNUM - WING A Number of Podium 1
Number of Basements -- Number of Slabs of Superstructure 20
Number of Plinth 2 Number of Stilts 1
Wing Name PRAJAPATI MAGNUM - WING B Number of Podium 1
Number of Basements -- Number of Slabs of Superstructure 20
Number of Plinth 2 Number of Stilts 1
Wing Name PRAJAPATI MAGNUM - WING C Number of Podium 1
Number of Basements -- Number of Slabs of Superstructure 20
Number of Plinth 2 Number of Stilts 1
Possession Availability
Possession Date 30/06/2021
Possession Availability as per RERA
Proposed Date of Completion 31-12-2019
Revised Proposed Date of Completion 30-06-2022
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 15
1 Stilt Floor 90
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 90
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 50
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 94
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 93
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 20